HV-48V-200Ah Installation Guide

Safety Warning​

⚠️ High voltage system installation must be performed by professionals:

  • High voltage electrical license required
  • Wear full insulating protective equipment
  • Follow operating procedures strictly
  • Ensure proper grounding

Installation Environment​

Room Requirements​

  • Dedicated battery room
  • Well ventilated
  • Temperature: -10°C ~ 50°C
  • Humidity < 85% RH
  • Floor load capacity ≥ 150kg/m²

Space Requirements​

  • Front/rear clearance ≥ 80cm
  • Top clearance ≥ 50cm
  • Side clearance ≥ 30cm

Installation Steps​

1. Foundation Check​

  1. Check floor levelness
  2. Confirm load capacity
  3. Verify ventilation system

2. Equipment Placement​

  1. Use forklift for handling
  2. Level and position
  3. Secure with anchor bolts

3. Electrical Connection​

⚠️ Disconnect all power before proceeding!

Three-phase power → Main breaker → Battery cabinet

4. Communication Connection​

  • CAN: 120Ω termination resistor
  • RS485: Shielded twisted pair

5. Grounding Connection​

Grounding resistance < 10Ω

Parallel Configuration​

Maximum Parallel Units​

  • Parallel units: Max 10
  • Total capacity: 96kWh

Verification Checklist​

ItemStandard
Insulation resistance≥ 100MΩ
Grounding resistance< 10Ω
Voltage testPass